A pediatric practice moves into 6,200 SF on the second floor of a Ballantyne medical office building on Monday, November 16. Every vendor between the lease and the first patient, on one board, chased until they deliver.
Patients scheduled from 8:00 am November 16. The date does not move.
Landlord side and tenant side, each with an owner and a date.
Architect and furniture. Both escalated to the broker today with options.
Miss the furniture order and the exam rooms arrive after the first patient.
| Vendor | Needed | Last touch | Status | If late, it holds up |
|---|---|---|---|---|
| Landlord's contractorTenant improvements, 6,200 SF | Substantial completion Nov 2 | Sep 30 | On track | Framing and rough-in passed |
| ArchitectRevised casework drawings | Were due Sep 25 | Sep 30 | Late | Contractor's casework order |
| Furniture dealerExam, waiting and staff furniture | Order by Oct 5 | Oct 1 | Escalated | Move-in, 5-week lead time |
| Cabling contractorData drops, 48 locations | Sign quote by Oct 6 | Sep 29 | Quote out | Rough-in before drywall |
| Internet providerFiber install | Order by Oct 9 | Sep 28 | Site survey Oct 6 | Phones, scheduling system |
| Equipment vendorExam tables, scales, vaccine fridges | Delivery Nov 12 | Sep 22 | Confirmed | None |
| SignageSuite and directory panels | Landlord approval | Sep 30 | With landlord | Fabrication |
| Building securityAccess badges, 22 staff | Staff list by Nov 6 | Sep 24 | Not started | Nothing yet |
| Electric utilityAccount in tenant's name | Start date Nov 2 | Sep 29 | Scheduled | None |
| Insurance agentCertificate naming the landlord | Before move access Nov 9 | Sep 29 | Wording fix | Move access, keys |
| MoversWeekend move, 2 crews | Book by Oct 16 | Sep 30 | 3 quotes in | Move-in |
Every vendor gets a touch at least twice a week until delivered. Anything that moves the move-in date goes to the broker the same day.
Hi Dana,
Writing for Morgan Hale at Queen City Tenant Advisors on the Suite 210 order. The practice signed off on the layout Tuesday. Two things to place the order this week:
Move-in is November 16, so we need it ordered by October 5.
Hi Dana, following up on the below. We still need the revised quote and the lead time. The order has to go in by Monday the 5th to make a November 16 move. Can you send both today?
The chase. Same thread, two lines, the deadline restated. No re-explaining.
Morgan, the furniture dealer hasn't answered two emails and a call since September 24. The order deadline is Monday. Options:
We recommend 1 today and 2 as the fallback Friday. Want us to make the call?
The escalation. It goes to the broker once the vendor's silence threatens the date, with priced options and a recommendation. A bare status note doesn't do that.
Hi Ken, the revised casework drawings were due September 25. The contractor can't release the casework order without them, and that order has a four-week lead. Can you confirm they'll be out by Friday, October 2? If one detail is holding it up, tell us which and we'll get the practice's answer today.
The ask gets narrower each time. The first email asked for drawings. This one names the order that is waiting, the lead time behind it and the one date that matters. It also offers to unblock the architect.
The landlord's contractor is copied because the delay holds up their schedule too. That keeps it from becoming the tenant's problem to solve.
Red is late today. The shaded band is move week. Furniture is the longest run that ends inside it, so it gets the most attention.
The agent's first draft named the wrong landlord entity. It was caught on review, not by the property manager two days before the move.
| Furniture | No answer since Sep 24. Options sent, recommendation is to call the manager. | Today |
| Casework | Drawings five days late. Contractor's order on hold. | Today |
| Signage | Landlord approval at day 8 of a 10-day review under the lease. | Watch |
| Day | What happens | Confirmed with |
|---|---|---|
| Mon Nov 9 | Move access opens. COI on file, freight elevator booked for Saturday, keys issued to the office manager. | Property manager |
| Tue Nov 10 | Fiber live and tested. Phones forwarded from the old office on a 72-hour overlap. | Internet provider |
| Thu Nov 12 | Exam tables, scales and vaccine fridges delivered. Fridges logged at temperature for 24 hours before vaccines arrive. | Equipment vendor |
| Fri Nov 13 | 22 badges active. Walkthrough with the office manager and the contractor's superintendent. | Building security |
| Sat Nov 14 | Two crews, 7:00 am start, freight elevator until 3:00 pm. | Movers |
| Mon Nov 16 | First patient, 8:00 am. | The practice |