Wrenfield Pediatrics  ·  Suite 210 move-in  ·  Mon Nov 16

Eleven vendors,
one move date.

Vendor follow-up board  ·  Ballantyne  ·  Charlotte, North Carolina
46days to move-in
11vendors, each with an owner and a date
2at risk this week
Oct 5the date that decides it
QUEEN CITYTENANT ADVISORS
01   Vendor board  ·  Thu Oct 1, 4:30 pm  ·  Hover a card for its full thread

Every vendor between the lease and the first patient.

Show
At risk2Late or escalated
Tenant sideOrder by Oct 5
Furniture dealerExam, waiting and staff furniture
DWDana WhitfieldAccount rep
Next Call Dana's manager today. Stock-finish fallback to the practice Friday.
EscalatedLast Oct 1
Landlord sideAsked for Oct 2
ArchitectRevised casework drawings
KAKen AbernathyProject architect
Next Call Friday at noon if the drawings are not in.
LateLast Sep 30
Chasing3Waiting on a vendor or the landlord
Landlord sideReview ends Oct 5
SignageSuite and directory panels
SMSheila MarrowProperty manager
Next Approval or comments by Monday, day 10 of the lease review.
With landlordLast Sep 30
Tenant sideFix by Oct 6
Insurance agentCertificate naming the landlord
RTRick TolliverCommercial agent
Next Corrected certificate by Tuesday, then to the property manager.
Wording fixLast Sep 29
Tenant sideSite survey Oct 6
Internet providerFiber install
JVJill VarnerBusiness sales
Next Meet the surveyor Tuesday. Order to the practice to sign by Oct 9.
Survey bookedLast Sep 28
With the practice2Waiting on a signature or a pick
Tenant sideSign by Oct 6
Cabling contractorData drops, 48 locations
OHOmar HaddixEstimator
Next Practice signs by Tuesday so rough-in starts Oct 9.
Quote outLast Sep 29
Tenant sidePick by Oct 9
MoversWeekend move, two crews
LPLorna PruittPractice administrator
Next Practice picks a quote by Oct 9. We book it by Oct 16.
3 quotes inLast Sep 30
Not started1Opens later, on purpose
Landlord sideStaff list by Nov 6
Building securityAccess badges, 22 staff
SMSheila MarrowProperty manager
Next Form on file. Staff list request to the practice Oct 26.
Not startedLast Sep 29
Opens later

Staff list request to the practice Oct 26

Phone forwarding set with the fiber order, 72-hour overlap

Old-office keys and walkthrough, after move-in

On track3Confirmed, checked weekly
Landlord sideComplete Nov 2
Landlord's contractorTenant improvements, 6,200 SF
WKWade KimbroughProject manager
Next Site meeting Tuesday. Confirm the casework install window.
On trackLast Sep 30
Tenant sideDelivery Nov 12
Equipment vendorExam tables, scales, vaccine fridges
NANell AshbyAccount manager
Next Weekly check. Freight elevator held for Nov 12.
ConfirmedLast Sep 29
Tenant sideStarts Nov 2
Electric utilityAccount in the practice's name
BUBusiness service deskUtility
Next Start date confirmed. Check again the week of Oct 26.
ScheduledLast Sep 29
Wrenfield Pediatrics, Suite 210Vendor board
02 / 06Queen City Tenant Advisors ·  Vendor follow-up boardSample deliverable: practice, landlord, vendors, people and figures are illustrative.
02   Critical path to Mon Nov 16

Two items are slipping. Both run into move week.

Late todayAt riskOriginal planLandlord sideTenant sideDeadline

Opens on move week. Swipe right to see where it started.

Sep 21Sep 28Oct 5Oct 12Oct 19Oct 26Nov 2Nov 9
Move week
Today, Oct 1
First patient, Nov 16, 8:00 am
Landlord side
Casework drawingsArchitect
4 business days late
Casework orderLandlord's contractor
4-week lead
Tenant improvementsLandlord's contractor
Inspections, occupancyLandlord's contractor
Punch listLandlord's contractor
SignageLandlord, sign shop
ReviewFabricationInstall
Tenant side
FurnitureFurniture dealer
Order Oct 5, 5-week leadInstall
CablingCabling contractor
SignRough-inDrywall
FiberInternet provider
SurveyOrderInstall
Certificate of insuranceInsurance agent
FixOn file
Electric accountUtility
Starts
EquipmentEquipment vendor
Delivery
BadgesBuilding security
Ask for listIssue
MoversMovers
PickBookMove
Furniture

The longest run that ends inside move week. An order on Oct 5 delivers Nov 9 with two business days to spare. Every day the order waits comes off that.

Casework

Drawings a week late pushed the four-week order to Nov 2. That leaves four business days to install it before move access.

Cabling

Rough-in has to finish before drywall starts Oct 19. That only works if the practice signs the quote by Oct 6.

Wrenfield Pediatrics, Suite 210Critical path
03 / 06Queen City Tenant Advisors ·  Vendor follow-up boardSample deliverable: practice, landlord, vendors, people and figures are illustrative.
03   Follow-ups, Sep 28 to Oct 1

20 touches this week. Two escalations.

Every ask carries a deadline and the reason for it. "By Oct 5, five-week lead" gets answered.
Three quiet business days, then a chase on the same thread. Two more, a call.
A date at risk reaches the broker the same day, with priced options.
Sent and loggedPick a thread
Furniture is at risk for November 164 in thread
Queen City Tenant Advisors · Operations
ToDana Whitfield, furniture dealer
CcMorgan Hale
The ask

Hi Dana,

Writing for Morgan Hale at Queen City Tenant Advisors on the Suite 210 order. The practice signed off on the layout Tuesday. Two things to place the order this week:

  1. The final quote with the exam room chairs swapped to the wipeable vinyl the practice picked.
  2. Your lead time from order to delivery. We are planning on five weeks.

Move-in is November 16, so we need it ordered by October 5.

Queen City Tenant Advisors · Operations
Hi Dana, following up on the below. We still need the revised quote and the lead time. The order has to go in by Monday the 5th to make a November 16 move. Can you send both today?
ToDana Whitfield
Chase

Hi Dana, following up on the below. We still need the revised quote and the lead time. The order has to go in by Monday the 5th to make a November 16 move. Can you send both today?

Call logged  ·  office line
Dana's line, voicemail. Left the Monday deadline and asked for a call back today.

Dana's line, voicemail. Left the Monday deadline and asked for a call back today.

Queen City Tenant Advisors · Operations
ToMorgan Hale
Escalation

Morgan, the furniture dealer hasn't answered two emails and a call since September 24. The order deadline is Monday. Options:

  1. Call Dana's manager today. It's the fastest fix if the quote just sat.
  2. Order the exam rooms from stock. Same line in a different finish, three weeks, about $1,900 less.
  3. Rent waiting room furniture for two weeks if the order slips. $640.

We recommend 1 today and 2 as the fallback Friday. Want us to make the call?

Casework drawings late, order on hold2 in thread
Queen City Tenant Advisors · Operations
ToKen Abernathy, project architect
CcWade Kimbrough, landlord's contractor; Morgan Hale
Chase

Hi Ken, the revised casework drawings were due September 25. The contractor can't release the casework order without them, and that order has a four-week lead. Can you confirm they'll be out by Friday, October 2?

If one detail is holding it up, tell us which and we'll get the practice's answer today.

Queen City Tenant Advisors · Operations
ToMorgan Hale
Escalation

Morgan, Ken hasn't answered the September 30 chase. The drawings are four business days late and the contractor's casework order, a four-week lead, is on hold. If nothing is in by Friday at noon we call Ken, then his principal. No decision needed from you yet.

Why the contractor is copied. The delay holds up their schedule too, so it doesn't become the practice's problem to solve. The ask names the order that is waiting, the lead time behind it and the one date that matters.

Mover quotes, side by side1 in thread
Queen City Tenant Advisors · Operations
ToLorna Pruitt, Wrenfield Pediatrics
CcMorgan Hale
Decision

Hi Lorna, all three mover quotes are in. The building gives us the freight elevator Saturday Nov 14 from 7:00 am to 3:00 pm, so the start time matters more than the price.

  1. A, $5,950. Two crews, 7:00 am start, elevator protection included.
  2. B, $5,200. One crew of six, 9:00 am start. Likely runs past 3:00.
  3. C, $7,600. Two crews plus Sunday unpacking.

We recommend A. Pick one by Friday Oct 9 and we'll book it and the elevator.

Certificate of insurance, two fixes1 in thread
Queen City Tenant Advisors · Operations
ToRick Tolliver, insurance agent
CcMorgan Hale
Fix

Hi Rick, thanks for the draft. Two fixes before it goes to the property manager:

  1. The additional insured has to be the landlord entity exactly as written in the lease, Section 11.3. The draft names the parent company.
  2. Add the property manager as an additional insured. It was left off.

Limits and the 30-day cancellation wording look right. Can you send the corrected certificate by Tuesday Oct 6?

Cabling quote for signature1 in thread
Queen City Tenant Advisors · Operations
ToLorna Pruitt, Wrenfield Pediatrics
CcMorgan Hale
Signature

Hi Lorna, the cabling quote is attached for signature: 48 data drops, $13,440. We checked the drop count room by room against the approved plan and it matches.

The crew has to finish rough-in before drywall starts October 19, so they need the signed quote by Tuesday Oct 6 to start on the 9th.

Signage review closes Oct 51 in thread
Queen City Tenant Advisors · Operations
ToSheila Marrow, property manager
CcMorgan Hale
Reminder

Hi Sheila, a reminder that the suite and directory sign proofs went to you September 21. Under the lease the landlord's review closes Monday, October 5. Approval or comments by then keeps fabrication on its three-week schedule. Thank you.

Access badges, Suite 2102 in thread
Queen City Tenant Advisors · Operations
ToSheila Marrow, property manager
Ask

Hi Sheila, the practice will need 22 access badges for a November 16 move. Can you send the badge request form and your lead time? We'll send the staff list early in November.

Sheila Marrow
ToQueen City Operations
Reply

Form attached. Five business days from the list. Badges can be active the Friday before.

Fiber site survey booked1 in thread
Call logged  ·  office line

Jill Varner, business sales. Site survey booked for Tuesday Oct 6 at 10:00 am. Order must be signed by Oct 9 for a Nov 4 to Nov 10 install. Confirmed the 72-hour phone forwarding can be added to the order.

Text  ·  to the field
OHOmar HaddixCabling contractor

Omar, it's Queen City ops for Suite 210 at Wrenfield. The practice has your quote and signs by Tue Oct 6. Can your crew still start rough-in Fri Oct 9? Drywall starts the 19th.

Yes. Oct 9 holds if it's signed by the 6th. Two techs, six working days.

Perfect. We'll text you the minute it's signed.

Text message
15Emails
3Calls
1Texts
1Site meetings
Wrenfield Pediatrics, Suite 210Follow-ups this week
04 / 06Queen City Tenant Advisors ·  Vendor follow-up boardSample deliverable: practice, landlord, vendors, people and figures are illustrative.
04   What the practice decides

Four decisions in the next eight days.

01Decide byFri Oct 2, noon

Furniture fallback

Order deadline Mon Oct 5. Dealer silent since Sep 24.

1Call Dana's manager todayWe make the call todayNo costRecommended
2Order exam rooms from stockFallback Friday: same line, other finish, 3 weeksAbout $1,900 lessFallback
3Rent waiting room furniture, 2 weeksOnly if the order slips past Nov 9$640
Decides: Practice, with Morgan Hale
02Decide byTue Oct 6

Cabling quote

Rough-in Oct 9 to 16 has to beat drywall on Oct 19.

1Sign as quoted, 48 dropsDrop count matches the approved plan$13,440Recommended
2Hold to add dropsAdded drops can go in after move-inRisks the Oct 9 start
Decides: Lorna Pruitt
03Decide byFri Oct 9

Fiber order

Survey Oct 6. Install Nov 4 to 10, live and tested Nov 10.

1Order with 72-hour phone forwardingPatients reach the practice all move weekendOld and new lines overlapRecommended
2Order without forwardingPhones dark Sat to Mon
Decides: Lorna Pruitt
04Decide byFri Oct 9

Movers

Freight elevator Sat Nov 14, 7:00 am to 3:00 pm only. Book by Oct 16.

ATwo crews, 7:00 am startFinishes inside the elevator window$5,950Recommended
BOne crew of six, 9:00 am startLikely runs past 3:00 pm$5,200
CTwo crews plus Sunday unpackingUnpacking is optional$7,600
Decides: Lorna Pruitt
Handled, nothing needed from you

Certificate of insurance, fixed before it bounced.

  • Landlord entity named exactly as in the lease, Section 11.3
  • Property manager added as additional insured
  • General liability $1M and $2M, umbrella $2M
  • 30-day notice of cancellation wording
  • Movers' certificate on file before the elevator is booked

The agent's first draft named the wrong landlord entity. It was caught on review, not by the property manager two days before the move.

Casework drawingsChased Sep 30 with the contractor copied. Call Friday at noon if they are not in.
Signage reviewDay 8 of 10. Approval or comments asked for by Mon Oct 5.
BadgesForm and lead time on file. Staff list request to Lorna Oct 26, due Nov 6.
Wrenfield Pediatrics, Suite 210Decisions this week
05 / 06Queen City Tenant Advisors ·  Vendor follow-up boardSample deliverable: practice, landlord, vendors, people and figures are illustrative.
05   Move week

Move week, step by step, and who confirms each one.

Mon Nov 9Move access opensCertificate on file, Saturday elevator held, keys to Lorna.Property manager
Mon Nov 9Furniture deliveredInstalled through Nov 11. At risk until it is ordered Oct 5.Furniture dealer
Tue Nov 10Fiber live, signs upLines tested. Old office phones forward for 72 hours.Internet provider
Thu Nov 12Equipment inFridges logged 24 hours before vaccines arrive.Equipment vendor
Fri Nov 13Badges and walkthrough22 badges active. Walkthrough with the superintendent.Building security
Sat Nov 14MoveTwo crews from 7:00 am, elevator until 3:00 pm. Booking due Oct 16.Movers
Mon Nov 16First patient, 8:00 amThe practice
After move-in, still on the board
Punch list closedSigned off with photos within 30 days.
Old space handed backKeys, badges and walkthrough, so the deposit comes back.
Old accounts closedElectric, fiber and alarm, the day after the move.
Allowance paid outInvoices and lien waivers to the landlord on time.
Wrenfield Pediatrics, Suite 210Move week